Solution 3 — Build the cost case

Reference answer for ../exercises/03_build_the_cost_case.md.

Headline: approve cache + batching — ~33% saving for 5 engineer-weeks, and both survive the platform migration. Decline distillation: it breaks even in 6.7 months against a model with about 7 months to live. Quantization is the interesting borderline case, and the argument that decides it is lifetime, not break-even.

All figures reproducible with tools/cost_model.py (an analytic model; the multipliers here were measured by the team, which is the only reason they are usable).


1. Baseline

demand        = 18 qps × 900 tokens          = 16,200 tokens/s
usable per GPU= 2,000 × 0.70                 =  1,400 tokens/s
GPUs          = ceil(16,200 / 1,400) = ceil(11.57) = 12        <- rounding matters
monthly       = 12 × $2.80 × 730             = $24,528
requests/month= 18 × 3,600 × 730             = 47.30M
$/1k requests = 24,528 / 47,304 × 1,000      = $0.5185

Note the rounding immediately: 11.57 GPUs of demand costs 12 GPUs of money. 0.43 GPUs — $879/month — is bought and never used, before anyone optimizes anything. This is why savings arrive in steps.

2. Every proposal

Proposal GPUs $/month Saving/mo Eng cost Break-even
Baseline 12 24,528 — — —
Exact-match cache (40% hit) 7 14,308 10,220 $18,000 1.8 mo
Better batching (×1.25) 10 20,440 4,088 $12,000 2.9 mo
INT8 quantization (×1.5) 8 16,352 8,176 $36,000 4.4 mo
Distilled student (×2.5) 5 10,220 14,308 $96,000 6.7 mo
Cache + batching + quantization 4 8,176 16,352 $66,000 4.0 mo

Worked example for the cache row, since the pattern is the same for all of them: demand × 0.60 = 9,720 → ceil(9,720/1,400) = 7 GPUs → 7 × 2.80 × 730 = $14,308. Saving 24,528 − 14,308 = $10,220/month; break-even 18,000 / 10,220 = 1.8 months.

3. The model-lifetime constraint changes the answer

Break-even alone would rank distillation as merely "slow". Against a 7-month model life it is disqualifying, and the reason generalises: an optimization coupled to a specific checkpoint has an expiry date, so its true return is saving × (remaining life − delivery time) − engineering cost, not saving × 12.

Delivery time matters and is usually left out. Two engineers working in parallel turn engineer- weeks into roughly half as many calendar weeks, so a 16-engineer-week project is ~2 months before it saves its first dollar — 2 of the 7 months, gone before the meter starts.

Proposal Model-agnostic? Delivery Saving months Net over the remaining 7 months
Cache yes — sits in front of whatever model serves ~0.4 mo 6.6 +$10,220 × 6.6 − $18,000 = +$49,500, and it keeps paying afterwards
Batching yes — a serving-path property ~0.3 mo 6.7 +$4,088 × 6.7 − $12,000 = +$15,400, keeps paying
Quantization no — quantized weights are per-checkpoint ~1.0 mo (incl. the gate) 6.0 +$8,176 × 6.0 − $36,000 = +$13,000, then pay the cost again
Distillation no — the student is the checkpoint ~2.0 mo 5.0 +$14,308 × 5.0 − $96,000 = −$24,500, a loss

Distillation loses about $24,500 under the stated timeline. That is a much stronger statement than "it takes 6.7 months to break even", and it is the sentence to lead with. It also does not depend on the quality risk, the eval work, or the re-distillation treadmill — all of which make it worse.

Quantization survives, but barely, and the shape matters: it returns $13,000 and then the migration consumes the asset, so you pay the $36,000 again. Against a model with a full life ahead of it the same project returns roughly $62,000 a year. Same project, same numbers, and the timing decides it.

4. The finance ask: 30%

Yes, and comfortably.

  • Cache alone: 41.7% reduction ($24,528 → $14,308) for 3 weeks and $18,000. This clears the ask on its own.
  • Cache + batching: 41.7% — the same 7 GPUs, because after the cache the batching multiplier does not remove another whole GPU (ceil(9,720 / 1,750) = 6… in fact it does: 6 GPUs, $12,264, 50.0%). Worth 2 more weeks for another ~$2,000/month.

That combination is 5 engineer-weeks ($30,000), delivers ~50% against a 30% ask, carries zero quality risk (identical outputs), and survives the platform migration. Delivery: roughly 6 weeks including the gate-free rollout, so the saving starts in month 2.

Recompute rather than assuming composition. The two optimizations do not simply add: caching cuts demand, and only then does the batching multiplier decide whether another whole GPU comes out. Always recompute the GPU count for the combination.

5. Recommendation, including the decline

Approve: exact-match cache (3 weeks), then batching (2 weeks). ~50% reduction, $30,000, no quality risk, both survive the migration.

Defer: INT8 quantization. It is a real $8,176/month, but it costs 6 weeks plus the quality gate (see exercise 2 — that gate is itself substantial work), and it must be redone after the migration. Revisit after the platform migration lands, when the work attaches to a model with a full life ahead of it.

Decline: the distilled student. The number: $96,000 of engineering, delivered ~2 months in, against $14,308/month for the ~5 months of model life that remain — a net loss of roughly $24,500, before counting the eval work, the maintenance, and the re-distillation the migration forces. It is not a close call, and it is not a judgement about distillation: the same proposal against a model with a three-year life would be an easy approval.

6. Opportunity cost

Five engineer-weeks is five weeks of roadmap not shipped. Framed for a director who does not care about GPUs:

"Five engineer-weeks buys a permanent $12,000/month reduction in serving cost — about $144,000 a year, against a one-off $30,000. It pays back in under three months and keeps paying after the platform migration. The question I can't answer alone is whether those same five weeks on the roadmap would generate more than $144,000 a year of value. If the feature they displace is worth more than that, we should not do this."

What I need from product to complete the argument: the expected annual value of the specific features displaced, and their timing. Without that, I can only present cost avoidance and let someone with the revenue picture make the call — and I should say so rather than presenting the cost saving as though it settles the matter.

Note the asymmetry that makes this an easy approval anyway: the saving is recurring and certain (no quality risk, measured multipliers), while roadmap value is uncertain. That does not always favour cost work, but it does when the payback is under three months.

7. Sensitivity

The single most fragile input is the 40% cache hit rate. It is the largest saving and the entire justification for the top recommendation.

  • At 40% (assumed): 7 GPUs, $10,220/month, break-even 1.8 months. Approve.
  • At 25%: demand 12,150 → ceil(12,150/1,400) = 9 GPUs → $18,396 → saving $6,132/month, break-even 2.9 months. Still approve.
  • At 15%: demand 13,770 → 10 GPUs → $20,440 → saving $4,088/month, break-even 4.4 months. Now it is no better than batching and costs 50% more effort — the ordering flips, and batching should go first.

So my answer flips at a hit rate around 15%. That is a wide margin below the assumed 40%, which is why I am comfortable — but it is also a one-day measurement (replay a week of the request log against a simulated cache) and I would run it before committing the three weeks. It would be embarrassing to spend $18,000 to discover the documents are not re-submitted as often as we thought.

The second-most-fragile input is the 7-month migration date, which is §8.

8. If the migration slips a year

Then distillation's arithmetic changes completely: ~19 months of life, less ~2 months to deliver, so 17 × $14,308 − $96,000 = +$147,000, and it becomes the highest-value item on the list. A slip does not merely soften the decline — it reverses it.

How to structure the decision so you are not badly wrong in either world:

  1. Do the model-agnostic work now, unconditionally. Cache and batching are correct in both worlds. They are also the only items that require no forecast at all, which is precisely why they go first — and it is worth noticing that the ladder's ordering already produced this answer without needing the forecast.
  2. Make the model-coupled work a gated decision with a named date. Write down: "if the migration has not landed or been firmly scheduled by month 4, we reopen quantization; by month 6, we reopen distillation." A decision with a review date is a different artifact from a decision that quietly expires.
  3. Ask for the migration's confidence interval, not its date. "Two quarters" from a platform team has a known distribution. If the honest answer is "somewhere between 6 and 18 months", the expected-value calculation should use that spread, and I would say so in the memo rather than pretending the point estimate is real.
  4. Reduce the coupling. If distillation is likely eventually, build the distillation pipeline (traffic logging, teacher scoring, eval harness) now — it is model-agnostic and it makes the eventual student a fraction of the 16 weeks. This converts a bet on a date into an investment that is correct either way, and it is the most valuable idea in this answer.

The "it depends on X" pivot: X is the migration date's distribution, not its point estimate. Firm within 7 months → cache + batching only. Uncertain, plausibly 18 months → add quantization now and build the distillation pipeline. Point estimates hide exactly the risk that decides this, which is why the recommendation is written as a schedule of gated decisions rather than a single verdict.

The email to Finance

We can reduce the ML serving line item for this service by about 50% — from $24,500 to roughly $12,300 per month — with five engineer-weeks of work (one-off ~$30,000), starting to take effect next month. Both changes are caching and request batching, which carry no model-quality risk and survive the upcoming platform migration; we are deliberately not pursuing model compression this cycle because the current model is due to be replaced before that work could pay for itself.